Lakeland Electric's New Power Plant Goes Online After Delays and Cost Overruns
Key Ideas
  • The McIntosh Reciprocal Engine Plant in Lakeland, Florida, has finally passed its final performance test and is now contributing 120 megawatts of power to Lakeland Electric customers.
  • The new plant features six high-efficiency, reciprocating internal combustion engines that can potentially be modified to use hydrogen fuel in the future.
  • Despite construction delays and cost overruns amounting to $40 million, the new power facility is seen as a positive addition to Lakeland Electric's power generation portfolio, comprising about 14% of the utility's capacity.
  • The utility also issued $70 million in municipal bonds to cover construction overruns and costs associated with a previous outage, allowing them to maintain steady customer rates while dealing with an aging flagship generator.
Lakeland Electric's new McIntosh Reciprocal Engine Plant, located in Lakeland, Florida, has finally come online after facing significant delays and cost overruns. The plant, equipped with six high-efficiency internal combustion engines, has the capacity to contribute 120 megawatts of power to the utility's customers. Despite the construction challenges, the plant is viewed as a valuable asset representing about 14% of Lakeland Electric's total capacity. The facility, which began construction in August 2022 and faced various setbacks including supply chain issues and a train derailment, finally completed testing and commissioning in April. Notably, the engines at the new plant can potentially be adapted to use hydrogen fuel in the future, showcasing a commitment to exploring renewable energy sources. To cover the construction overruns and costs from a previous outage, Lakeland Electric issued $70 million in municipal bonds, ensuring that customer rates remain stable. However, this increased the utility's debt ratio to 53%, nearing the 55% ceiling set to maintain a favorable rating. The utility's flagship generator, Unit 5, is currently undergoing maintenance and is crucial for Lakeland Electric's operations, expected to remain in service until at least 2032. Looking ahead, Lakeland Electric may explore options like purchasing power from other utilities or entering long-term agreements instead of investing in new power plant construction, given the uncertainties in the political and economic landscape. The completion of the McIntosh Reciprocal Engine Plant represents a positive milestone for Lakeland Electric, enhancing its power generation capabilities and contributing to a more diverse energy portfolio.
ADVANCEH2

Our vision is to be the world's leading online platform for advancing the use of hydrogen as a critical piece needed to deliver net-zero initiatives and the promise of a clean H2 energy future.

© 2025 AdvanceH2, LLC. All rights reserved.